Timeline of Titan Krios installation

Jan.02.2017 -- Crates arrived

Jan.02.2017 – Crates arrived

Jan. 05. 2017 – Unpacking and installation started

Jan.12.2017 – Microscope body rolled into enclosure

Installation of the FEG gun

Feb.10.2017 – The gun beamed for the first time on site

Feb.28.2017 – Installation of GIF/K2 started

Mar.29.2017 – Sign-off

July.01.2017 – Open to Yale community

♦ Photo credit: Chris Incarvito